Europe must get its State aid rules right to have any chance of delivering climate neutrality

The European Commission is revising its 2014 State aid guidelines for environment and energy. These guidelines define what national Government can and cannot do to support climate and energy projects, notably in wind energy.

PRESS RELEASE EcofinConcept markets a further 749 kWp solar park to a private investor

EcofinConcept markets a further 749 kWp solar park to a private investor
EcofinConcept GmbH, the specialist for renewable energy projects, has marketed another solar park to an investor from northern Germany.

EU funding for electricity infrastructure will help wind energy reach consumers

The European Commission has announced the winners of its latest Connecting Europe Facility (CEF) funding round. It set aside €873 million to invest in key European energy infrastructure projects. Of the 17 energy projects selected for funding, eight are in electricity. With €680 million, it’s the first CEF round in which electricity received more funding than gas.

Expansion figures for the first half of 2017 in Germany Onshore wind energy – Strong expansion in transition, significant risks in 2018/2019

Gross expansion of onshore wind energy by 2,281 megawatts (MW), which equals 790 wind power plants, as high as expected in the first half of 2017 Industry implementing the projects approved through the end of 2016 – transition effect will cease in 2018

Prospect following the first round of tendering for onshore wind energy:
Considerable planning uncertainty due to the success of non-approved projects
Cost reduction continues
Lawmakers must stipulate the Federal Immission Control Act (BImSchG) approval as the uniform prequalification; the respective provision for the two tendering processes in 2018 must become permanently valid
It is vital that capacities in non-implemented projects be retendered to achieve a successful energy transition

Kaufangebot: VESTAS Windpark mit 3 in Betrieb befindlichen V90

Verkauf eines fertig errichteten und in Betrieb befindlichen 6 MW VESTAS Bestandswindpark

3 VESTAS V90-2.0 MW Windkraftanlagen
insgesamt 6 MW (6.000 kW) Nennleistung
90m Rotordurchmesser
95 bzw. 105m Nabenhöhe

Inbetriebnahme: im 4. Quartal 2006 erfolgt

VESTAS Full-Service Vereinbarung (AOM Vollwartungsvertrag)

Der Windpark ist fertig errichtet und in Betrieb

Gesicherte Abnahme und Vergütung des erzeugten Stroms gemäß Erneuerbare-Energien-Gesetz (EEG)

Zusatzvergütung aus Direktvermarktung

technischer Betriebsführungsvertrag und kaufmännischer Geschäftsbesorgungsvertrag

Vermittlung Bestandsanlagen NEG Micon NM 1.000/60 mit Standort

Verkauf Angebot Windkraftanlagen

Windpark NEG Micon NM 60/1000 mit Standort in Sachsen-Anhalt als Investition zum Weiterbetrieb

Hersteller: NEG Micon (jetzt VESTAS)
Typ: NM 1000/60
Nennleistung: 1.000 kW (1 MW)
Nabenhöhe: 80m
Rotordurchmesser: 60m

Vermittlung einer NORDEX N50 Windkraftanlage ohne Standort

Verkaufsangebot: Windenergieanlage NORDEX N50 mit 800 kW Nennleistung

Typ: NORDEX N50

Anzahl: 1 Stück

Baujahr: 2000
Nennleistung: 800 kW
Rotordurchmesser: 50 m
Nabenhöhe: 70 m; Stahlrohrturm

ohne Trafo